Pre-Bid Meeting: RFP 17B Polyester Overlay - Superstructure West/East Approaches & Main Span Structure

Wednesday, 10 January 2018 10:00 AM - 11:00 AM PST

11 Golden Shore, Ste 330, Long Beach, CA, 90802, United States

Register Now

Registration

Sale ended

General Partial Approval - Free

Enter your discount code

  • Fee
  • Total amount

1. Select Seats

2. Review and Proceed

Wednesday, 10 January 2018 10:00 AM - 11:00 AM PST

SFI JV Corporate Office, 11 Golden Shore, Ste 330, Long Beach, CA, 90802, United States.

Attendance is Mandatory…


SFI JV is seeking contractors capable of providing all labor, material and equipment for the following scope of work related to the construction of the Gerald Desmond Bridge Replacement Project.

Please note, the project has a UDBE participation goal of 11%.

 

Scope of Work:


The scope of work for the Pavement Reinforcing for the Gerald Desmond Bridge cable stay bridge and approaches shall include the following: The cost of all necessary labor, material, equipment, supplies, supervision, safety, and quality control required to complete the work in accordance with the contract documents and as noted below. Each Contract scope shall be bid and accepted as a complete package. All material and equipment must be approved by SFI prior to purchase and installation.

 

During this meeting, we will review:

  • Scope of Work for RFP 17B - Estimated Value of $10 Million
  • UDBE Participation
  • Additional Opportunities for this Bid: Materials, Sweepers, Water Trucks, Flat Bed Trucks